I-84, Garrity Interchange Bridge; 11th Ave. to Garrity Blvd., Nampa

   
  
 

Construction Update

   

Interstate 84 (I-84)
Expect I-84 to be reduced to one lane in each direction at night excluding weekends, between the Franklin Interchange and Robinson Road overpass while crews work along the shoulders.

The lane closures will take place between 10 p.m. and 5 a.m. Both lanes will be open by the morning commute and during the day. Overnight closures are not expected to occur on Friday or Saturday nights. Weekly closures will continue until the shoulder work is completed.


Garrity Boulevard
Two southbound lanes and one northbound lane have been moved inside the bridge piers beneath the Garrity Interchange bridges while crews use the outside lanes to work on the bridges.

The speed limit has been lowered to 35 on Garrity Boulevard and 55 mph on I-84 through the construction zones.

    

Background

   
In 2001, the Community Planning Association of Southwest Idaho (COMPASS) and ITD completed a cooperative planning effort called the I-84 Corridor Study. The study examined the transportation system needs for the I-84 corridor from the WYE Interchange to Idaho 44 west of Caldwell.

The study recommended specific improvements that warranted further evaluation and implementation. The recommendation to widen the interstate segment between Franklin Boulevard and Garrity Boulevard was included in the COMPASS study.
    

Funding

   
This project is funded by the GARVEE Transportation Program. The program uses Grant Anticipation Revenue Vehicle (GARVEE) bonds to expedite interstate improvements.

    

Schedule

   
Environmental clearance for this project was obtained in April 2009 through a Finding of No Significant Impact (FONSI) on the I-84, Karcher Interchange to Five Mile Environmental Study. Preliminary design was completed in April 2009, and final design was completed in September 2009. Right-of-way acquisition was completed in September 2009. Construction began in January 2010, with anticipated completion in June 2011.
    

Compliance with Title VI of the Civil Rights Act

   
The Idaho Transportation Department (ITD) is committed to compliance with Title VI of the Civil Rights Act of 1964 and all related regulations and directives. ITD assures that no person shall on the grounds of race, color, national origin, gender, age, or disability be excluded from participation in, be denied the benefits of, or be otherwise subjected to discrimination under any ITD service, program, or activity. The department also assures that every effort will be made to prevent discrimination through the impacts of its programs, policies, and activities on minority and low-income populations. In addition, the department will take reasonable steps to provide meaningful access to services for persons with Limited English Proficiency.
    
 

Contact

   

GARVEE_Logo.jpg
Contact
comments@itd.idaho.gov
Phone: (208) 334-4444
TDD: (208) 334-4458

ITD Home Page

ITD Projects Page
    
 

 

   
    
 

 

   
    
Maximize 

Brochures/Postcards

   
    
Maximize 

Meetings/Hearings

   
    
Maximize 

News Releases

   
    
  Terms Of Use  Privacy Statement